I-265 Ohio River Bridges Project
Project Name: I-265 Ohio River Bridges Project
Project Date: November 2014
Location: Louisville, IN
Partners: Walsh Vinci Construction, Applied Research Associates
Customer Group(s):
-
Pavement Engineering Consultants
-
Earthwork/Grading Contractors
Ingios Engineers Involved: E. Tom Cackler, David White, Pavana Vennapusa
Tech briefs:
Pavement Mechanistic-Empirical (ME) Design Verification using APLT Testing
Challenge: The Ohio River Bridges project was a massive $2.3B transportation project in the Louisville metro area. The project involved new bridges and connecting highways with numerous grade crossings, 32 lane-miles of roadway and roughly 450,000 SY of concrete pavement. During construction, incomplete QC/QA data needed for acceptance of the pavement foundation construction along a 2-mile stretch of roadway began causing delays to the late fall paving program. Rapid deployment of a solution to verify the pavement foundation properties was needed to keep the project on schedule.
Solution: Ingios® Geotechnics’ engineers immediately launched into a review of pavement designs by working closely with the pavement designers to develop a methodology to translate design requirements to target field-values. The solution involved continuous mapping of the 2-mile stretch of prepared base-material using Ingios’ COMP-Score® RT (CRT) mapping; by retrofitting Contractor’s compactor at the site in less than one day.
An Automated Plate Load Testing (APLT) plan consisting of cyclic plate load tests using 18-inch and 30-inch diameter plates was used to measure in-situ composite resilient modulus values to provide site-specific calibration. Calibration testing demonstrated a regression coefficient R2 > 0.9 for predicting resilient modulus using the CRT mapping results.
Benefits: CRT mapping provided continuous video recording of the results, as well as color-coded spatial mapping to display areas of compliance. Walsh Construction was alerted immediately to areas of non-compliance that did not meet the minimum pavement foundation design values and flagged for rework prior to paving. Results of the monitoring provided the
confidence for the design/build project team to address the localized areas and move forward with paving on the project that required a 2-year warranty and 30-year operation and maintenance requirement.